The following time-line diagram represents the cyclic activities involved in the production of AIS documents.

AIRAC Dates: this date is based on the International Civil Aviation Organization (ICAO) Aeronautical Information Regulation and Control (AIRAC) cycle of every 28 days.

Actual dates for a particular document are shown in the tables below.

Notification of changes to owned data or information should be submitted via the ADO Portal or approved for implementation via CRC. Please ensure the change is complete and submitted as it is to read in the AIP.

For any particular Amendment Cycle, time must be allowed for a proposed documentation change to be verified and validated prior to the cut-off date. Note: schedules are prepared a long way in advance and the cut-off dates shown below should be regarded as guidance only. Depending on circumstances, Airservices may need to make changes to future cut-off dates. Such changes to the Document Amendment Calendar will be posted on this web page and updated in the ADO Portal as they occur.

2026 Amendment Cycle

2603 19/03/2026
ERSA 19 MAR 2026 13/11/2025
DAP A/L 186 13/11/2025
AIP A/L 126 27/11/2025
2607 09/07/2026
MAP 71 / DAH 27/11/2025**
ERSA 09 JUL 2026 19/02/2026
DAP A/L 187 19/02/2026
AIP A/L 127 12/03/2026
2609 03/09/2026
ERSA 03 SEP 2026 14/05/2026
DAP A/L 188 14/05/2026
AIP A/L 128 11/06/2026
2612 26/11/2026
MAP 72 / DAH 11/06/2026**
ERSA 26 NOV 2026 06/08/2026
DAP A/L 189 06/08/2026
AIP A/L 129 10/09/2026

2027 Amendment Cycle

2703 18/03/2027
ERSA 18MAR2027 11/11/2026
DAP A/L 190 11/11/2026
AIP A/L 130 26/11/2026
2707 10/06/2027
MAP 73/DAH 26/11/2026**
ERSA 10JUN2027 18/02/2027
DAP A/L 191 18/02/2027
AIP A/L 131 11/03/2027
2709 2/09/2027
ERSA 02SEP2027 13/05/2027
DAP A/L 192 13/05/2027
AIP A/L 131 10/06/2027
2712 25/11/2027
MAP 74/DAH 10/06/2027**
ERSA 25NOV2027 5/08/2027
DAP A/L 193 5/08/2027
AIP A/L 132 9/09/2027

* Cut-off

This is the last date where approved change requests (e.g. CRC, RFC, DCR) to the AIP must be submitted to AIS Data Integrity (docs.amend@airservicesaustralia.com).

All consultation and approvals by other units (internal and external to Airservices) must be completed prior to this date. Change requests received after this date will be incorporated in the next available publication cycle.

**Approved changes to Airspaces or ATS Routes (e.g. ACP) must be submitted to the Airspace Designers 10 working days prior to the cut-off.

Privacy Statement

Where appropriate, personal information may be disclosed to airports or other related parties, in the course of verifying these amendments.

Airservices will not use your personal information for any other purpose, nor disclose it to any other unrelated party, without your consent or if we are required or authorised to disclose that information by law.